Share and Follow
CLEARWATER, Fla. (WFLA) – Crews were at work Thursday stabilizing and repairing a cracked pillar in a Clearwater Beach condo building.
On Tuesday, residents were forced to evacuate from the South Beach III condominium building on Sand Key.
The split prompted a massive response on Gulf Boulevard. Sixty people were forced to evacuate, and some residents were carried out on stretchers.
Residents will not be able to return home until the project is complete.
“I live on the 12th floor,” said resident Scott May. “All of a sudden, I got (a) knock, two firemen on the door hard that we had to get out immediately. I am wearing the exact same clothes that I wore when I left, Tuesday, coming down from the building.”
Officials said the crack was discovered amid the condo renovation project to the garage floor.
It’s one of many renovations taking place over recent months.
Last year, an engineering firm conducted a milestone inspection for the Clearwater Key Association, South Beach III Condominium at 1460 Gulf Boulevard.
The City of Clearwater released the following statement about the recent milestone inspection report conducted by Karins Engineering:
“Those documents were provided to their Community Association in August and September of 2024, and the city does not have record of receiving these required building milestone inspection reports by the Dec. 31, 2024, deadline. Per Florida Statute, buildings 30 years old before July 1, 2022, must have their initial inspection by Dec. 31, 2024, and meet all the statutory requirements in order to be in compliance.”
On Wednesday, city officials received the phase 1 milestone inspection reports that were issued on August 8, 2024, and Sept. 26, 2024.
The report states that the engineer did not observe conditions that would compromise the safety of the building for its intended use and occupancy.
“I don’t think it can hurt to have a second opinion,” May said. “People’s lives are at stake. If we go back up there, of course, we want to know that we’re safe.”
The city issued a permit to a general contractor for temporary shoring. Officials said there will be a threshold inspection to verify the work and to allow occupancy of the building. Additional work will be needed to complete more substantial repairs.
According to officials, the Clearwater Building Official will not allow residents to return to the building until a structural engineer delivers a report with confirmation that the structure is stable and safe to occupy.
Leaders with the Clearwater Fire and Rescue Division said construction crews saw a crack in one of the beams, noticed the split was widening and called first responders.
The 12-story, 140-unit condo building was constructed in 1980. According to the Clearwater permitting website, the structure was inspected last May.
The Red Cross is assisting displaced residents. The condo association told residents that it could be three to four more days before until structural engineers verify the building is safe to re-enter.
On Thursday, the condo association sent this update to residents:
“While the building is still under no access, we are working on a plan to have resident entry for emergency retrieval of personal items. The City and the Engineer continue to work on stabilizing the building.
We anticipate written authorization for emergency access from Karins Engineering within the next 24 hours.“