HomeNewsPiddington camp could be built before judges rule on its legality

Piddington camp could be built before judges rule on its legality

An asylum accommodation centre near the Oxfordshire village of Piddington could begin operating before the High Court decides whether the plans are lawful, the area’s MP has warned.

Calum Miller, MP for Bicester and Woodstock, said he was given an updated timetable during talks with Home Office minister Anna Turley.

The proposed schedule would see work on the migrant accommodation site start in January, with the centre opening in April, he said.

Communities Secretary Angela Rayner granted full planning permission last week to convert the former military facility at MoD Bicester into asylum accommodation.

However, campaign group Wrong Plan, Wrong Site has sought a judicial review of the decision, although the case has not yet been heard.

Mr Miller said starting construction before the High Court ruling could ‘waste taxpayers’ money’ on a project that might ultimately not go ahead.

In a letter setting out the details of the meeting, the Liberal Democrat MP said Ms Turley had indicated that the Home Office hoped to complete its full business case and obtain final ministerial approval by the end of 2026. That would allow building work to begin in the new year.

He wrote: ‘I told the minister that I believe this timetable is unrealistic. The site is not currently connected to water or electricity, significant questions remain over the cost, and the future of essential bomb disposal training has still not been resolved.

‘The full business case must be published so residents can understand what is being proposed, how much it will cost and how ministers could possibly justify the scheme.’

According to the letter, Ms Turley agreed to take the issues away and provide answers ‘in full’.

Under the proposed schedule, construction MoD Bicester (pictured) could begin in January, with the centre opening in April, according to the local MP

The proposed timetable would see construction at MoD Bicester (pictured) begin in January, with the asylum centre opening in April, according to the local MP

Calum Miller, the MP for Bicester and Woodstock, said he had been told an updated timeline for the site during a meeting with Home Office minister Anna Turley

Calum Miller, MP for Bicester and Woodstock, said Home Office minister Anna Turley had outlined a revised timetable during their meeting

Border security minister Anna Turley has defended the proposal, saying the centre is needed to reduce the Government’s reliance on hotels for asylum seekers.

She said the facility would be self-contained and offer basic services, reducing the need for residents to leave the site. It would also have round-the-clock security and CCTV.

But in the Commons this week, Shadow women and equalities minister Joy Morrissey accused the Government of placing women and girls in Piddington at greater risk.

‘The risks posed by horrific crimes committed by other illegal migrant men against girls as young as 12 were known, yet ministers chose to use emergency powers and disregard local opinion,’ she said.

‘They decided that not one minister needed to meet residents before the decision was taken. They ignored police warnings about the possibility of increased crime.

‘They have imposed 1,250 illegal migrant men on a village of just 350 people.’

The planning application attracted 3,177 objections and only one expression of support.

Ms Morrissey added: ‘I can say with certainty that ministers have got this decision categorically wrong. Their choice will have consequences, and they will have to live with them.

‘Why, then, do ministers believe it was appropriate to use emergency powers to bypass local planning scrutiny?’

Ms Turley responded by saying the Conservatives’ ‘brass neck’ was ‘astonishing’.

‘I wonder whether (Ms Morrissey) regrets the decisions taken by her government when it opened camps at Wethersfield and Crowborough, both of which are providing a much safer and more secure way to accommodate asylum seekers,’ she said.

‘She referred to concerns about local crime, but I wonder whether she has visited Wethersfield and listened to the fact that, despite operating for several years, there is no evidence of crime increasing in the area.’

A car passes a sign opposing the asylum centre near Piddington

A vehicle passes a sign campaigning against the proposed asylum centre near Piddington

‘Indeed, Essex Police chief constable said on September 11 that crime connected to the Wethersfield site was very low and that there was no reason for the public to be concerned about criminality linked to the facility.’

Ms Turley said local residents were entitled to express their concerns and had done so through an ‘imaginative and powerful campaign’.

Mr Miller also accused the Government of quietly announcing the decision after Parliament rose on Thursday. He claimed running the site could cost more than £1 billion over a decade.

Ms Turley said she could not discuss the figures, but maintained that existing asylum centres were ‘significantly cheaper’ than hotel accommodation.

The Government has pledged to stop housing asylum seekers in hotels and instead use former military locations.

Wethersfield and Crowborough are already operating. Alongside MoD Bicester, sites in Barnham, Norfolk, and Linton-on-Ouse, North Yorkshire, have also been identified.

Decisions on those two sites are understood not to have been made.

A Home Office spokesman said: ‘The Government is working towards a fairer distribution of asylum accommodation across the country and has saved more than £1 billion in costs since the election.

‘This includes closing asylum hotels and moving people into alternative accommodation, including former military sites. These facilities are designed to be self-contained and will have 24/7 security and CCTV to limit their impact on surrounding communities.

‘Large sites such as Wethersfield have operated for several years, with no evidence of rising crime in the area.

‘Planning permission means we can continue developing proposals for MoD Bicester. Any decision of this kind is subject to public safety considerations, particularly the safety of women and girls.’