APOPKA, Fla. – A heavily traveled section of Park Avenue near one of Apopka’s community parks could soon be redesigned to improve safety for people walking and biking between the park and a nearby residential area.
An Orange County traffic study recorded 14 crashes at Park Avenue and East Orange Street, beside Kit Land Nelson Park. One crash involved a pedestrian, while another involved a bicyclist.
On Nov. 12, the Apopka Community Redevelopment Agency authorized $167,150 for engineering and design work focused on pedestrian safety improvements at the intersection.
That funding covers planning and design—not construction. The distinction has fueled questions about traffic, missing sidewalk links and whether the proposed project will ultimately be built.
News 6 asked city officials to address those concerns.
[COVERING APOPKA: Pedestrians raise concerns as intersection improvements remain unfinished]
A park, a neighborhood and no marked pedestrian crossing
Park Avenue separates homes from Kit Land Nelson Park, creating a difficult crossing for residents who want to reach the park on foot or by bicycle, according to city officials.
“You have residents on one side, and you have this beautiful park, and zero pedestrian crossings,” Apopka spokesperson Steven Montiero told News 6.
Without a nearby marked crossing, Montiero said pedestrians and cyclists may choose to cross Park Avenue instead of walking farther to reach a traffic signal.
“The danger that presents itself is the pedestrians crossing the roadway, and the car is not expecting that,” Montiero said. “So we’re trying to mitigate that.”
The Orange County study identified the intersection as a safety concern for drivers, pedestrians and bicyclists.
The city could not immediately say when the 14 crashes occurred or provide details on the number that resulted in injuries.
What improvements are planned for Park Avenue?
The proposed pedestrian safety project includes:
-
A marked crosswalk for pedestrians.
-
Flashing beacons to alert drivers when pedestrians are crossing.
-
A pedestrian refuge area in the center of the roadway.
-
New sidewalk links.
-
Changes to the median and roadway layout.
-
More pedestrian warning signs.
-
Curb upgrades that meet ADA accessibility standards.
-
Drainage upgrades.
Montiero said the intersection offers the city an opportunity to add pedestrian infrastructure that is currently absent.
“So right here, we’re starting with a blank canvas, basically,” Montiero said.
The proposed refuge area would give pedestrians a designated place to pause while crossing. Flashing beacons would provide an additional warning to approaching motorists.
[WATCH: How Apopka plans to fix a multimillion-gallon problem]
How much will Apopka’s pedestrian safety project cost?
The Apopka Community Redevelopment Agency approved $167,150 for the project’s engineering design phase.
Construction is expected to cost another $450,000 to $500,000. Together, design and construction are estimated at roughly $617,000 to $667,000.
The Nov. 12 vote authorized design work only; construction will require separate funding.
Montiero said construction money is expected to come from either the Community Redevelopment Agency or the city. He also said he is confident the funding will be available.
News 6 gets answers to concerns surrounding the project
Several issues were discussed during the Nov. 12 Community Redevelopment Agency meeting, including:
-
Incomplete sidewalk connections around the intersection.
-
Possible traffic backups caused by median changes and turn restrictions.
-
Whether a conventional traffic signal might be more effective.
-
Whether construction will follow after the design work is finished.
News 6 asked the city to respond to each concern.
CONCERN 1: Missing sidewalk connections
Residents questioned how people would safely reach the proposed crosswalk if sidewalks do not connect to it from nearby streets.
In a written statement, the city acknowledged the issue and said improving pedestrian access is now a priority.
“The City of Apopka recognizes the concerns that have been raised regarding sidewalk connectivity in this area and improving pedestrian access has become a priority for this administration,” the city said.
“Our teams are actively working on plans to complete these connections and provide safer, more accessible routes for pedestrians and bicyclists.”
[WATCH: Apopka gets nearly $6M to fix reclaimed-water pressure problems]
CONCERN 2: Potential traffic backups and turning restrictions
The planned median and roadway changes raised concerns about how drivers will move through the intersection after the project is completed.
City officials said construction could cause temporary delays but do not expect a major long-term effect on traffic.
“Of course, with any infrastructure improvement comes the possibility of temporary inconveniences. I often say things sometimes have to get a little worse before they get better,” the city said.
“While residents and motorists may experience some slowdowns during construction, we do not anticipate significant traffic impacts, particularly given that this area does not currently experience substantial vehicular congestion.”
The city did not specifically explain how any permanent turn restrictions could affect drivers once the work is complete.
CONCERN 3: Would a traditional traffic signal be more effective?
Some officials also questioned whether a standard traffic light would offer a better solution than the proposed illuminated pedestrian crossing.
The city said its recommendation was based on an evaluation of the intersection.
“Following a study of the area, it was determined that an illuminated pedestrian crosswalk would be the most effective solution to improve safety and connectivity,” the city said.
The written response did not offer a detailed side-by-side analysis of the pedestrian beacon and a conventional traffic signal.
CONCERN 4: Will the project actually be built?
Because construction requires funding beyond the approved design contract, residents asked whether the project would advance beyond the planning phase.
News 6 asked Montiero how certain the city was that the improvements would be constructed. His answer was unequivocal.
“Let me be very clear. This pedestrian safety project is happening,” Montiero said.
He said the Community Redevelopment Agency or the city would provide the construction funding.
“This project’s gonna be completed for its residents,” Montiero said.
The city likewise said it does not currently expect delays.
“This remains a priority for the city and at this time, there are no anticipated delays in moving the project forward. Once the design receives final approval, we expect to proceed with construction and bring this important improvement to our community.”
Still, although city officials expressed confidence that funding will be secured, News 6 has not independently verified a formal appropriation for the construction phase.
When could construction be completed?
Residents will have to wait before using the new crossing.
Montiero said the engineering plans still must go through additional review and receive final approval.
After approval, the city expects the intersection improvements to take about 18 months to complete.
That estimate does not necessarily start with the Nov. 12 vote approving design funding.
Officials have not announced a specific construction start date.
What is Apopka doing to keep pedestrians safe in the meantime?
Until the project moves forward, the city said it has increased law enforcement presence in the area and stepped up messaging about pedestrian safety.
Montiero said Apopka police officers have been actively monitoring the intersection.
“We know that it is not fully capable of safe pedestrian crossings. That’s why we’re enhancing the area,” Montiero said.
Despite unresolved questions about funding, design and traffic effects, the city says the project is intended to make the intersection safer for everyone who uses it.
“Ultimately, this project is about making Apopka a safer, more connected community for everyone, whether you’re walking, riding a bicycle, or driving through the area,” the city said in its written response.